A schedule of values (SOV) is the breakdown of your subcontract into lines of work, each with a dollar value, that add up exactly to the contract sum. Once the general contractor approves it, every pay application you send bills a percent complete against those lines, until the job is closed out.
Getting it right at the start saves trouble every month after. A schedule that is too coarse gets your pay apps questioned. One that is front-loaded gets sent back. One with no clear place for change orders turns every change into an argument about which line it belongs to. This guide walks through building one for a specialty subcontract, with a worked example for a $480,000 electrical job.
Why general contractors require one
The GC bills the owner every month, and the owner, the architect and often the owner's lender have to agree that the work billed is really in place. Nobody can judge "40 percent of the electrical" on a site walk. They can judge whether level 1 rough-in is done or the switchgear is set. The schedule of values gives everyone the same lines to measure against. For the GC it does three jobs:
- Payment control. Each month's billing is checked line by line against progress on site, so nobody is paid ahead of the work.
- The GC's own pay app. Your billing rolls up into the GC's schedule of values to the owner, usually under the cost code for your trade. If your lines don't map onto theirs, someone re-keys your numbers every month.
- Protection if you don't finish. The value left on unfinished lines, plus the retainage held, is what the GC has to pay someone else to complete your scope.
Most subcontracts require an approved schedule of values before the first pay application, and many let the GC reject one and ask for more detail.
How the schedule of values becomes the G703
On a G702/G703-style pay application, the G702 is the one-page summary, and the G703 continuation sheet behind it is your schedule of values with billing columns added. AIA's G703 labels its columns with letters, and most pay app forms and GC portals keep the same order:
- A, item number, and B, description of work: from your schedule.
- C, scheduled value: from your schedule, plus approved change orders.
- D, work completed on previous applications, and E, work completed this period.
- F, materials presently stored: delivered but not yet installed.
- G, total completed and stored to date (D + E + F), and G ÷ C, the percent complete.
- H, balance to finish (C − G), and I, retainage on the line.
Columns A to C are the schedule itself. They don't change from month to month unless a change order adds a line, and everything to their right is calculated from them. The totals of columns G and I become lines 4 and 5 of the G702 summary, so a mistake in the schedule carries straight through to the check you receive. What is retainage explains the G702 lines in more detail.
Building one line by line
- Start from your estimate. Your bid already breaks the job into labor, material and equipment by area or system. Group it into lines the GC can check on site, rather than inventing a split that exists only for billing.
- Ask for the GC's format first. Many GCs send a template, line items or cost codes, especially when they bill through a portal. Use them, even if it means splitting your estimate differently.
- Split by how the work is built. Rough-in and finish work by building, floor, area or phase; systems such as fire alarm or low voltage as their own lines.
- Separate material from labor on major equipment. Switchgear, fixtures and other expensive material can then be billed as stored materials when it arrives, against its own line.
- Keep general conditions modest and separate. Mobilization, bonds and insurance, submittals and temporary power get their own lines, priced at what they cost.
- Leave value for closeout. A line for testing, as-builts, O&M manuals and warranty gives the GC something to hold until they are delivered, and gives you something to bill when they are.
- Spread overhead and profit across the lines in proportion to their cost, unless the GC asks for them separately. Loading the profit onto early lines is front-loading.
- Check the total to the cent. The lines must add up exactly to the original contract sum. Fix a rounding difference on the largest line, not with a "miscellaneous" line.
The free schedule of values template checks the total against the contract sum as you type, and downloads as Excel with formulas or as a CSV.
Worked example: a $480,000 electrical subcontract
An electrical subcontractor signs a $480,000 subcontract on a two-story medical office building, with 10 percent retainage. Its schedule of values has 17 lines:
| Item | Description | Scheduled value | % of contract |
|---|---|---|---|
| 1 | Mobilization, bonds & insurance | $9,000.00 | 1.88% |
| 2 | Submittals & shop drawings | $5,000.00 | 1.04% |
| 3 | Temporary power & lighting | $14,000.00 | 2.92% |
| 4 | Underground & site conduit | $36,000.00 | 7.5% |
| 5 | Switchgear & service entrance (material) | $52,000.00 | 10.83% |
| 6 | Switchgear & service entrance (labor) | $18,000.00 | 3.75% |
| 7 | Panelboards & transformers | $43,000.00 | 8.96% |
| 8 | Feeders | $46,000.00 | 9.58% |
| 9 | Branch rough-in, level 1 | $58,000.00 | 12.08% |
| 10 | Branch rough-in, level 2 | $54,000.00 | 11.25% |
| 11 | Lighting fixtures (material) | $41,000.00 | 8.54% |
| 12 | Lighting fixtures & controls (labor) | $27,000.00 | 5.63% |
| 13 | Devices & trim | $22,000.00 | 4.58% |
| 14 | Fire alarm system | $34,000.00 | 7.08% |
| 15 | Low-voltage rough-in | $8,000.00 | 1.67% |
| 16 | Testing & commissioning | $8,000.00 | 1.67% |
| 17 | Closeout, O&M manuals, as-builts & warranty | $5,000.00 | 1.04% |
| Original contract sum | $480,000.00 | 100% |
Mobilization, bonds and insurance is 1.88% of the contract, not a large share of it. Switchgear is split into material and labor, so the gear can be billed as stored material when it is delivered. Rough-in is split by level, so the GC can check each floor, and closeout is its own line, worth $5,000.
On the first pay app, mobilization is billed in full, submittals at 80 percent, temporary power at 60 percent and underground conduit at 75 percent. The continuation sheet carries the schedule's columns unchanged and fills in the rest:
| A | B, description | C, scheduled | E, this period | G ÷ C | H, to finish | I, retainage |
|---|---|---|---|---|---|---|
| 1 | Mobilization, bonds & insurance | $9,000.00 | $9,000.00 | 100% | $0.00 | $900.00 |
| 2 | Submittals & shop drawings | $5,000.00 | $4,000.00 | 80% | $1,000.00 | $400.00 |
| 3 | Temporary power & lighting | $14,000.00 | $8,400.00 | 60% | $5,600.00 | $840.00 |
| 4 | Underground & site conduit | $36,000.00 | $27,000.00 | 75% | $9,000.00 | $2,700.00 |
| … | Lines 5 to 17: nothing billed yet | |||||
| Total, all 17 lines | $480,000.00 | $48,400.00 | 10.08% | $431,600.00 | $4,840.00 | |
Total completed to date is $48,400, 10.08% of the contract. The GC holds $4,840 in retainage and the payment due is $43,560. Next month, this period's work moves to "previous applications" and only new work is billed. The free pay application generator does that math for you.
Front-loading
Front-loading means putting more value on work done early and less on work done late, so more of the contract is billed in the first months. Suppose the subcontractor had put $48,000 on mobilization, 10% of the contract, and taken the extra $39,000 out of fixture labor, devices and trim, testing and closeout. With the same progress, the first pay app would be due $78,660 instead of $43,560.
That is why GCs look for it. Those four late lines would be worth $23,000 instead of $62,000, less than the work costs, so if the subcontractor left the job, the money left in the contract would not pay anyone to finish it. A schedule like this is normally sent back, some contracts forbid it, and it costs credibility you will want later when you ask for retainage to be reduced or released. Price each line at its cost plus its share of overhead and profit, and be ready to show how you got there.
Change orders
Once the schedule is approved, the original lines stay as they are. Approved change orders are added below them as new lines, each with its own scheduled value, and billed the same way. On the G702, the original contract sum doesn't change; net change orders and the contract sum to date do.
In the example, the owner adds EV charging circuits in the parking lot for $18,500 and deletes data rough-in in the storage rooms for $3,000. The bottom of the continuation sheet now reads:
| Item | Description | Scheduled value |
|---|---|---|
| 1–17 | Original schedule of values | $480,000.00 |
| CO1 | Change order 1: EV charging circuits, parking lot | $18,500.00 |
| CO2 | Change order 2: delete data rough-in, storage rooms | -$3,000.00 |
| Contract sum to date | $495,500.00 |
A few habits keep change orders from turning into billing disputes:
- Bill only approved change orders. Pending or disputed work usually can't go on the continuation sheet until it is signed, however far along it is. Track it separately and push for approval.
- One line per change order, with its number, so the GC can match it to their log.
- Show a deduct as a negative line rather than cutting an original line, unless the GC wants it done another way.
- Expect retainage on change order work at the contract rate, unless the change order says otherwise.
- Don't move value between original lines to absorb a change. A reallocation needs the GC's written agreement.
Build yours free
Build your schedule in the free schedule of values template and check it against the contract sum, then open it in the free pay application generator to bill against it. Neither needs an account.
Frequently asked questions
Who prepares the schedule of values?
Each subcontractor prepares the schedule of values for its own subcontract and submits it to the general contractor for approval. The GC prepares its own schedule for the whole project, which the owner or architect approves, and your lines often roll up into it.
Is the schedule of values the same as the G703?
The G703-style continuation sheet is the schedule of values with billing columns added. Its first three columns are the item number, description and scheduled value from your approved schedule; the rest show work completed, stored materials, percent complete, balance to finish and retainage on each line.
Can I change a schedule of values after it is approved?
Only with the general contractor's agreement. Moving value from one line to another after approval usually needs a written request and a reason. New or deleted work is handled with change orders on their own lines, so the original lines stay as approved.
Can I bill for materials before they are installed?
Often yes, if your subcontract allows it. Materials delivered and stored on site, or in an approved off-site location, are billed in the stored materials column against their line. GCs commonly ask for supplier invoices, proof of insurance or a bill of sale first, and retainage is usually held on them too.
How detailed should a schedule of values be?
Detailed enough that the GC can check your percent complete on each line during a site walk. Split large scopes by floor, area or phase, and split material from labor on major equipment. If the GC gives you a format or cost codes, use them.
This guide is general information, not legal advice. Retainage limits and release deadlines vary by state and by contract.