What is retainage in construction?

Updated

Retainage is a share of each progress payment, usually 5 to 10 percent, that the owner or general contractor holds back until the work is finished. It is money you have already earned and billed, but you are not paid it until the end of the job, and often months after that.

It is also called retention. The owner holds it as security: if work is left unfinished, turns out defective, or a supplier down the line goes unpaid, the held money is there to cover it. For a subcontractor it is often most of the profit on the job. If your margin is 10 percent and the GC holds 10 percent, the money you have not been paid is roughly your whole profit until retainage is released.

This guide is for the people in a subcontractor's office who bill retainage and chase it: how it is calculated, when it should come back, what slows it down, and how to keep track of it across every job.

How retainage works on a pay app

Progress billing is cumulative. Each month you report the value of work completed to date on each line of your schedule of values, plus any materials stored on site and not yet installed. The GC withholds the retainage percentage from that running total, subtracts what earlier pay apps already certified, and pays the difference. Because retainage is recalculated on the total to date, the amount held grows every month until the job is done.

On a G702-style application summary the lines work like this:

  • Line 4, total completed and stored to date: everything you have earned so far.
  • Line 5, retainage: the rate applied to that total, split into 5a (on completed work) and 5b (on stored materials), since some contracts hold a different rate on each.
  • Line 6, total earned less retainage: line 4 minus line 5.
  • Line 7, less previous certificates for payment: line 6 from the last pay app.
  • Line 8, current payment due: line 6 minus line 7, the check you should receive.

The G703-style continuation sheet shows the same retainage line by line across your schedule of values. Two things are easy to miss. First, retainage does not reduce your contract: it is billed and owed, just not yet paid. Second, line 9, balance to finish including retainage, counts the money held as still owed to you. To put a pay app together, use the free pay application generator, which does this math for you.

Typical rates and step-downs

Ten percent has long been the classic rate, and 5 percent is common, especially on public work, where statutes often cap it. Some contracts hold a different rate on stored materials than on installed work.

Many contracts lower the rate partway through the job, most often once the work is 50 percent complete. This is called a step-down or retainage reduction, and it comes in two forms:

  • New work only. Retainage already held stays held, and work completed after the milestone is held at the lower rate. On a 10-to-5 step-down at 50 percent, that works out to 10 percent on the first half of the contract and 5 percent on the second.
  • Reduce what is held. The lower rate applies to all work to date, so the excess already held is released with that month's payment.

A step-down is often not automatic. Contracts commonly make it conditional on satisfactory progress and the owner's or architect's approval, and some require you to ask for it in writing. Some contracts, and some states, let a contractor post a retainage bond or put securities in escrow instead of having cash held.

Release timing and caps on the rate vary by state, by contract, and between public and private projects. This guide does not cover state-specific rules. Read your subcontract first, then check your state's statutes or ask a construction attorney.

A worked example

An electrical subcontractor signs a $480,000 subcontract with 10 percent retainage and no change orders. Here are four pay apps, the last one at 100 percent complete:

Pay appCompleteCompleted to dateRetainage heldPayment due
120%$96,000.00$9,600.00$86,400.00
245%$216,000.00$21,600.00$108,000.00
365%$312,000.00$31,200.00$86,400.00
4100%$480,000.00$48,000.00$151,200.00

At 20 percent complete the sub has earned $96,000, the GC holds $9,600, and the check is $86,400. By the third pay app, at 65 percent, $31,200 is held. On the final pay app the work is done, but the GC still holds $48,000, and that money only arrives once release is approved, usually billed on a separate retainage invoice.

Now add a step-down to 5 percent on new work once the job is 50 percent complete. The second pay app, at 45 percent, holds $21,600 as before. On the third, the work between 45 and 50 percent is held at 10 percent and the work from 50 to 65 percent at 5 percent, so retainage is $27,600 instead of $31,200, and the check is $90,000 instead of $86,400. At completion the GC holds $36,000 instead of $48,000.

Try your own numbers. The calculator uses the same math as the pay apps in RetainageBack.

Retainage calculatorFree
Completed to date$312,000.00
Retainage held$31,200.00
Earned less retainage$280,800.00

Retainage for subcontractors vs general contractors

Retainage flows down the contract chain. The owner holds retainage from the general contractor, and the GC holds retainage from each subcontractor, usually at least the same rate. Many subcontracts include a flow-down clause that ties your terms to the GC's contract with the owner, and a pay-when-paid or pay-if-paid clause that ties your payment to the owner paying the GC. How far those clauses can be enforced varies by state. Some states also limit how much a GC can hold from a sub compared with what the owner holds from the GC.

The two sides experience retainage differently:

  • A general contractor has retainage on both sides of the ledger: money the owner owes it and money it owes its subs. It deals with the owner directly and sees closeout as it happens.
  • A subcontractor mostly has retainage owed to it, and depends on the GC both to pass the money down and to tell it where closeout stands. If the subcontract ties release to completion of the whole project rather than your scope, a trade that finishes early, such as sitework, concrete or steel, can wait a year or more after its last day on site.

Flow-down can work in your favor too. If the owner's contract with the GC steps retainage down at 50 percent, or releases it by phase, ask the GC whether the same terms apply to your subcontract, and ask before you sign if you can. It is also worth asking the GC each month what the owner has released to it, since that is often the first sign your own release is due.

When retainage is released, and what slows it down

Release usually follows a sequence like this:

  1. The project, or your scope if the contract allows it, reaches substantial completion.
  2. The punch list is finished and signed off.
  3. You hand over closeout items: warranties, as-built drawings, operation and maintenance manuals, spare materials (attic stock), and anything else your subcontract lists.
  4. You bill the retainage and include the lien waivers the contract requires.
  5. The owner releases retainage to the GC, and the GC pays you.

Many states set a deadline for paying retainage once the work is accepted, and charge interest when it is late, but the rules differ by state and between public and private work. Any one of these steps can stall:

  • Punch list items that sit open because the crew has moved to the next job.
  • A missing warranty letter, O&M manual or as-built that nobody realized was outstanding.
  • Lien waivers still needed from your own suppliers or lower-tier subs.
  • The owner holding all retainage until the whole building is accepted or occupied.
  • Backcharges, disputed change orders or a closeout dispute between the GC and the owner.
  • No retainage invoice ever sent, or one sent once and never followed up.

The last one is the most common and the easiest to fix. Lien rights also have strict deadlines that vary by state, so do not let them pass while you wait on a release.

Tracking retainage across jobs

The amounts add up quickly. A subcontractor with eight jobs holding an average of $30,000 each has $240,000 of earned money sitting with GCs, often more than the business keeps in the bank. The owner of the company will want that number, and which jobs it sits on, without waiting for someone to build a spreadsheet.

With three to ten active GC jobs, retainage builds up in many places at once, and no single report shows it. Your accounts receivable aging shows retainage as old invoices or not at all, depending on how it was entered, and a spreadsheet drifts out of date the first month nobody updates it. Keep one list with a row per job and these columns:

  • GC, job and contract value, with the retainage rate and any step-down terms.
  • Retainage held to date, from the latest pay app (line 5).
  • Retainage released to date and the amount still outstanding.
  • What triggers release under the contract, and the substantial completion date.
  • Closeout documents and lien waivers still owed.
  • The date you last asked for release, and the date of your next follow-up.

Sort it by how long retainage has been outstanding since substantial completion. The jobs at the top are where your money is stuck.

Free retainage report

See every dollar of retainage your GCs owe you, in one list

Upload the pay apps you already sent, and RetainageBack builds the list above for every job and GC, aged by how long the money has been held. No card needed.

Get your free retainage report

How to request retainage release

  1. Read the release terms. Find what triggers release in your subcontract (your scope's completion, the project's substantial completion, or the owner's release to the GC) and any notice or document requirements.
  2. Get the completion date in writing. Ask the GC to confirm the substantial completion date for your scope or the project, by email at least.
  3. Close out the punch list. Get written sign-off, not just a verbal okay from the superintendent.
  4. Send every closeout document in one package. Use the GC's closeout list, and keep a copy of what you sent and when.
  5. Bill the retainage. Submit a retainage pay app or invoice for the full amount held, with the lien waiver the contract calls for. A conditional waiver, one that only takes effect once you are paid, is the safer choice where your contract and state allow it.
  6. Follow up on a schedule. Ask where the release stands every two weeks, in writing, and note each request. If the GC says it is waiting on the owner, ask what the owner still needs.
  7. Escalate when it stalls. Go from the project manager to the GC's accounting department, then to a principal. If deadlines pass, a construction attorney can tell you what prompt payment and lien rights you have in your state.

A short, specific request gets a faster answer than a general one. For example:

Subject: Retainage release, Riverside Medical Office, Pay App 14

Hi Dana, our scope reached substantial completion on September 12, the punch list was signed off on October 3, and the closeout package went to your office on October 10. Attached is our retainage invoice for$48,000.00 with a conditional final lien waiver.

Can you confirm the invoice is in this month's draw to the owner, and let us know if anything else is needed on our side? Thank you.

Retainage receivable in accounting

Retainage is earned revenue whose collection is delayed. Most contractors keep it out of regular accounts receivable, in a separate asset account usually called retainage receivable. That keeps your AR aging honest: invoices that are 120 days old because of retainage are not the same problem as invoices a GC simply has not paid.

A common setup in QuickBooks Online works like this:

  • Create an Other Current Asset account named Retainage Receivable.
  • Invoice the full amount of work completed this period, then add a negative retainage line posted to Retainage Receivable. Revenue is recorded in full, and AR shows only what the GC should pay now.
  • When retainage is released, invoice it with a positive line posted to the same account. That moves it out of Retainage Receivable and into AR, and the GC's payment clears it.
  • Partial releases, including the excess paid back when a step-down reduces what is held, are invoiced the same way for the amount released.

Reconcile the Retainage Receivable balance for each job to retainage held on the latest pay app, less anything released. If they don't match, a retainage line was missed or posted to the wrong job. If you hold retainage from your own subs, the mirror image is a retainage payable liability account. Banks and sureties read these balances, so ask your CPA how they want retainage presented on your financial statements.

Frequently asked questions

Is retainage the same as retention?

Yes. Retainage and retention are two names for the same thing: a share of each progress payment that is held back until the work is substantially complete.

How much retainage is normal?

Most contracts hold 5 to 10 percent of each payment. Many reduce it to 5 percent or less once the job is half complete. Some states cap the rate, especially on public projects, so check your contract and your state's rules.

When should retainage be released?

Usually after substantial completion, once closeout documents and lien waivers are in and the owner has paid the general contractor. Contracts and state prompt-payment laws often set a deadline for the release after that.

Do I bill retainage separately?

Usually yes. Retainage held on earlier pay apps is requested with a final or retainage-only pay application, often with a final lien waiver. Your contract says what the GC needs to see before releasing it.

How do I keep track of retainage across jobs?

Keep one list per job with retainage held, released and still outstanding, the substantial completion date and the date you last asked for release. RetainageBack builds that list from the pay apps you already send.

This guide is general information, not legal advice. Retainage limits and release deadlines vary by state and by contract.